Maintenance dredging
Case studyJamnagar intake dredging and rock removal
Maintenance dredging of the channel and stilling basin that feed the Jamnagar seawater intake.
115,000 m³ Material removed
Maintenance dredging
Maintenance dredging at a seawater intake and stilling basin during plant operations.

Deep Dredging removed silt and hard strata from the intake channel and stilling basin at Reliance Industries’ Jamnagar facility. High swell, wind and continuous plant operations were major constraints.
The campaign finished within the scheduled period and recorded 20,000 work hours without an incident.